Project Schedule

‘Request for Proposal’ Package Finalized April 2013
Site Preparation Work
Comox Valley and Campbell River Sites
March – December 2013
Collaborative Meetings April – August 2013
RFP Submission Evaluations October 2013 – March 2014
Identify Preferred Proponent
Project Agreement Negotiations
April – June 2014
Financial Close June 30, 2014
Ground Breaking Ceremonies August 7, 2014
Design and Construction of New Facilities June 2014 – April 2017
Service Commencement – Project Completion April 30, 2017
Commissioning and Transition Period Summer – Fall 2017
Move-In Late Fall 2017